CF: Detailed timeline emerges for new stadium construction and San Siro demolition

1 hour ago 31

With AC Milan and Inter now the owners of San Siro, the roadmap can be officially laid out, and a report has looked at the plans.

There has been a lot of talk in the past few weeks about what will happen with San Siro and when. Of course, there is a lot to do, from demolition to building the new stadium. It is not a short-term project, so things will happen gradually.

It seems that the final step, as it were, will be taken in May 2032, so in almost seven years. Again, not a short process.

New plans

Today, Calcio e Finanza have provided a detailed breakdown of the plans from the next few weeks to the next few years. The end date of the project is actually closer to 2036, rather than 2032, it seems too.

Phase 1 of development: Construction of the new stadium and demolition of the Meazza

  • Preliminary and definitive design, drafting of the implementation plan and Technical-Economic Feasibility Project – from March 2025 to February 2026 (12 months) 
  • Implementation Plan Presentation – February 2026 
  • Approval of the implementation plan – from February 2026 to February 2027 (12 months) 
  • Pre-investigation of the Technical-Economic Feasibility Project – from January 2026 to June 2026 (6 months) 
  • Presentation of the Technical-Economic Feasibility Project – July 2026 
  • Environmental Impact Assessment plus Conference of Services for final project approval and issuing of permits (Stadium Law) – from July 2026 to March 2027 (8 months) 
  • Signing of the agreement for the Technical-Economic Feasibility Project and issuance and publication of the Regional Authorisation Provision – March 2027 
  • Signing of the urban planning agreement – ​​March 2027 
  • Executive design of the urbanisation works to offset costs and subsequent project validation – from August 2026 to January 2027 (6 months) 
  • Public tender for the construction of urbanisation works – from March 2027 to August 2027 (5 months) 
  • Executive design of private works – from October 2026 to July 2027 (9 months) 
  • Final authorisations for the executive design of private works – from March 2027 to July 2027 (4 months) 
  • Reclamation works, including the redevelopment of the Meazza external areas, from December 2025 to July 2027 (19 months) 
  • Mobilisation and preparation of the construction site – from April 2027 to October 2027 (6 months) 
  • Construction of urbanisation works – from August 2027 to January 2030 (29 months)
  • Construction of urbanisation works – from August 2027 to January 2030 (29 months)
  • Construction of the new Milan stadium – from October 2027 to October 2030 (36 months)
  • Final testing – January 2030 to December 2030 (11 months)
  • INAUGURATION OF THE NEW MILAN STADIUM – December 2030
  • Public tender for the demolition of the Meazza stadium – from October 2030 to March 2031 (5 months)
  • Demolition and partial conservation activities of the Meazza stadium – from April 2031 to May 2032 (14 months)
new san siroImage: Il Giorno

Phase 2 of development: Multipurpose area and Meazza redevelopment

  • Preparation and submission of the detailed urban planning proposal for Phase 2 – from July 2027 to January 2028 (6 months)
  • Approval of the detailed urban planning project for phase 2 – from January 2028 to December 2030 (36 months)
  • Preparation and submission of the Final Project to the competent authorities – from January 2031 to July 2031 (7 months)
  • Approval of the final project, signing of the agreement and issuing of the permits – from August 2031 to February 2032
  • Executive design of phase 2 works and final authorisations – from March 2032 to January 2033 (11 months)
  • Remediation interventions and subsequent certification – from September 2031 to June 2033 (22 months)
  • Mobilisation and implementation of phase 2 works, including the redevelopment of the Meazza – from July 2033 to November 2035 (29 months)
  • INAUGURATION OF THE MULTIPURPOSE AREA IN PHASE 2, INCLUDING THE REFURBISHED MEAZZA STADIUM

It is interesting to see that everything is planned in two phases, as it were. However, with it being two projects, effectively, it does make a lot of sense.